The ERC also approved the P1.36-billion Sumangga 138-kV Substation Project, which is due for completion by March 31, 2028. It seeks to alleviate overloading on the Ormoc-Baybay 69-kV Line.
The NGCP is required to finish the project on or before Aug. 31, 2028. The proposed Sumangga 138-kV substation aims to resolve overloading issues in the existing Ormoc-Baybay 69-kV line and seeks ...
Ameren is hosting open houses to discuss the Grand Tower Crossing Project, aimed at enhancing energy reliability with a new 138-kV transmission line. The project seeks community feedback for its 2028 ...
Among the approved projects are the 230-kilovolt (kV) Granada substation in Bacolod; the 138-kV Sumangga substation in Ormoc; the 138-kV La Carlota substation in Negros Occidental; and one ...
In its February 12 meeting, the agency approved NGCP’s proposed 230-kiloVolt (kV) Granada substation project costing P1,943,977,100.96; the Sumangga 138-kV substation project, P1,361,891,878.73 ...